File #: 25-060    Name:
Type: Consent Agenda Status: Agenda Ready
File created: 5/28/2025 In control: Town Council
On agenda: 6/17/2025 Final action:
Title: Authorization for the Town Manager to Enter into a Contract with Design-Build Firm for Town Hall Renovation PURPOSE: To seek Council authorization for the Town Manager to negotiate and enter into a contract not to exceed $750,000 with the selected design-build firm to complete phase 1 of the Town Hall building design and renovation project.
Attachments: 1. A - 6/20/23 Resolution Approving Unassigned Fund Balance for Town Hall Renovations, 2. B - Posted RFQ, 3. C - Resolution - Town Hall Renovation

Title

Authorization for the Town Manager to Enter into a Contract with Design-Build Firm for Town Hall Renovation

 

PURPOSE: To seek Council authorization for the Town Manager to negotiate and enter into a contract not to exceed $750,000 with the selected design-build firm to complete phase 1 of the Town Hall building design and renovation project.

end

Department

DEPARTMENT: Public Works, Finance

end

Council Direction

COUNCIL DIRECTION:

__X Race/Equity   __X Climate   __X Comprehensive Plan ____Other

Council Direction Statement

On June 20, 2023, the Carrboro Town Council approved a resolution authorizing the use of unassigned fund balance of $1 million for professional services, such as architects, engineers, consultants and other professionals needed for the design and construction of renovations for Town Hall.  See Attachment A - Resolution approving Unassigned Fund Balance for Town Hall Renovations. The renovation is intended to improve functionality, accessibility, and energy efficiency.

end

Information

INFORMATION: On April 8, 2025, the Town posted a Request for Qualifications for Design-Build Services for the Town Hall.  A qualifications-based selection process was conducted in accordance with North Carolina General Statutes, resulting in the shortlisting and interview of six design-build teams. Following evaluation, a preferred firm will be identified based on qualifications, experience, and proposed approach. The posting for RFQs is attached as Attachment B - Posted RFQ.

end

Fiscal and Staff Impact

FISCAL IMPACT: The fiscal impact for phase 1 of the Town Hall design and renovation project will be up to $750,000 to be funded out of the Capital Projects fund. These funds were previously allocated for this project on June 20, 2023.

end

Recommendation

RECOMMENDATION: Staff recommend that the Town Council approve the attached resolution, allowing the Town Manager to award a contract in an amount not to exceed $750,000 to the selected design-build firm to complete phase 1 of the Town Hall design and renovation project.