File #: 22-141    Version: 1 Name:
Type: Agendas Status: Passed
File created: 4/20/2022 In control: Town Council
On agenda: 4/26/2022 Final action: 4/26/2022
Title: Permit Extension Request for Previously Issued Conditional Use Permit for Veridia AIS PURPOSE: The purpose of this item is for Town Council to consider approving a request for an extension of the date when a Conditional Use Permit would otherwise expire for Veridia AIS CUP. Town Staff recommends approval of the request.
Attachments: 1. Attachment A - Resolution, 2. Attachment B - Staff Report, 3. Attachment C - Letter from Applicant, 4. Attachment D - CUP Document

TITLE: Title

Permit Extension Request for Previously Issued Conditional Use Permit for Veridia AIS

PURPOSE:  The purpose of this item is for Town Council to consider approving a request for an extension of the date when a Conditional Use Permit would otherwise expire for Veridia AIS CUP. Town Staff recommends approval of the request.

body

DEPARTMENT: Planning Department

 

CONTACT INFORMATION: Marty Roupe, Development Review Administrator, mroupe@carrboronc.gov <mailto:mroupe@carrboronc.gov> or 919-918-7333

 

INFORMATION: On behalf of Sustainable Properties, LLC, Mr. David Bell has requested an extension of the date on which a previously issued Conditional Use Permit (CUP) would otherwise expire on April 26, 2022. The Board of Aldermen originally granted this CUP on April 26, 2011. The permit allows construction of a major subdivision consisting of 39 residential dwelling units. Construction of the project has not commenced.

 

The applicant has submitted a letter, included as Attachment C, related to compliance with LUO Section 15-62 and including information about their continuing efforts to build the project. Of note, substantial progress has been made with two different nonprofit agencies with work continuing now with both respective agencies. The letter requests a two-year extension to allow for this work to continue in a manner that may preserve elements of and build upon the project that has already been approved.

 

FISCAL & STAFF IMPACT: The applicant has paid the applicable fee associated with this request.  No other impact noted.

 

RECOMMENDATION:r Town Staff recommends that Town Council adopt the attached resolution approving the permit extension request. The new expiration date for the permit would be April 26, 2024.