TITLE: Title
Update on the Rogers Road Sewer Project, Proposed Utility District, Community Outreach and Interlocal Agreement
PURPOSE: The purpose of this agenda item is to provide the Board of Aldermen an opportunity to receive information and discuss the status of the Rogers Road Sewer Project, Community Outreach, and Management and Funding.
body
DEPARTMENT: Planning
CONTACT INFORMATION: Patricia McGuire - 919-918-7327; pmcguire@townofcarrboro.org
INFORMATION: This update seeks to provide the Board of Aldermen with information on the status of surveying work, engineering design and permitting of the Rogers Road sewer project, the community outreach/community first planning effort, and the framework and requirements for the proposed utility district. A draft interlocal agreement for cost-sharing has been prepared. Input from the Board of Aldermen on the provisions of the agreement and the water and sewer utility district is being sought at this time.
Engineering and Community Outreach. Work on the Rogers Road sewer project has continued since the Board's last report on June 2nd. Following execution of an interlocal agreement between Orange County and OWASA, the services of AECOM were secured to design and prepare permit applications for the project. Mary Darr, OWASA's Director of Planning and Engineering has prepared a project update (Attachment B) and will be in attendance to provide additional information and respond to any questions. In mid-July, Orange County executed an agreement with the Marion Cheek Jackson Center which, in partnership with the Rogers-Eubanks Neighborhood Association, will provide support for outreach and engagement and to facilitate a community first planning effort (as described in the project outline attached to the interlocal agreement between Orange County and the Jackson Center). Copies of the agreements between these two entities and Orange County are included as Attachments C and D. On July 28th, a comm...
Click here for full text