File #: 22-101    Version: 1 Name:
Type: Agendas Status: Agenda Ready
File created: 3/28/2022 In control: Board of Aldermen
On agenda: 4/5/2022 Final action:
Title: Public Hearing on Financing for the 203 South Greensboro Street Property and Adoption of Resolution Supporting Application to the Local Government Commission PURPOSE: The purpose of this item is to take comments from the public on a proposed financing contract for the Town's share of the acquisition, construction, and equipping the planned 203 South Greensboro Street Project and adopt a resolution supporting an application to the Local Government Commission.
Attachments: 1. Attachment A: Resolution for LGC Application
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TITLE: Title
Public Hearing on Financing for the 203 South Greensboro Street Property and Adoption of Resolution Supporting Application to the Local Government Commission

PURPOSE: The purpose of this item is to take comments from the public on a proposed financing contract for the Town's share of the acquisition, construction, and equipping the planned 203 South Greensboro Street Project and adopt a resolution supporting an application to the Local Government Commission.
body
DEPARTMENT: Town Manager, Finance

CONTACT INFORMATION: Richard J. White III, Town Manager, 919-918-7315; Arche McAdoo, Finance Officer, 919-918-7439; Bob Jessup, Bond Counsel, 919-933-9891.

INFORMATION: On March 15, 2022 the Carrboro Town Council and the Orange County Board of Commissioners approved the Guaranteed Maximum Price (GMP) provided by Barnhill Contracting Company in the amount of $34,692,067 to complete construction of a building and associated parking at 203 South Greensboro Street to provide for the Orange County Southern Branch Library, Orange County Skills Development Center, Carrboro Recreation, Parks and Cultural Resources, WCOM Radio, and other uses.

The total project cost including design, construction and furniture, fixtures and equipment is $41,174,840. The County will pay $22,218,882 of the total project costs; and the Town's share of the project costs is $18,955,958 and will be paid as follows:

a. Tax exempt financing in the amount of approximately $12,595,000 for Design and Construction;
b. Cash contribution of $6,319,358 for FF & E, contingency, and construction; and,
c. Cash contribution of $41,600 from Stormwater Utility Enterprise Fund for soil
cell.

North Carolina law requires that the Town's installment financing contract in the amount not to exceed $12,650,000 be approved by the North Carolina Local Government Commission. In addition to holding a public hearing, the governing body must make certain findings of fact to support t...

Click here for full text