File #: 17-217    Version: 1 Name:
Type: Agendas Status: Passed
File created: 6/19/2017 In control: Board of Aldermen
On agenda: 6/27/2017 Final action: 6/27/2017
Title: Public Hearing on 100% Review of the Martin Luther King Jr Park Construction Design and Authorize the Town Manager to Award Construction Contract PURPOSE: The purpose of this agenda item is to provide the Mayor and Board members an opportunity to review and approve the 100% construction plans for Martin Luther King Jr Park along with granting the Town Manager the authority to award the construction contract
Attachments: 1. Attachment A - A RESOLUTION TO APPROVE THE MARTIN LUTHER KING JR, 2. Attachment B - 100% MLK Jr Park Presentation

TITLE: Title

 Public Hearing on 100% Review of the Martin Luther King Jr Park Construction Design and Authorize the Town Manager to Award Construction Contract        

PURPOSE:   The purpose of this agenda item is to provide the Mayor and Board members an opportunity to review and approve the 100% construction plans for Martin Luther King Jr Park along with granting the Town Manager the authority to award the construction contract  

body

DEPARTMENT:   Recreation and Parks          

 

CONTACT INFORMATION:     Anita Jones-McNair - 919-918-7381, amcnair@townofcarrboro.org <mailto:amcnair@townofcarrboro.org> and Wendell Rodgers - 919-918-7371, wrodgers@townofcarrboro.org <mailto:wrodgers@townofcarrboro.org>      

 

INFORMATION:  Stewart Inc. will present the 100% construction plans for the park.  Should the Board of Aldermen decide to approve the design plans, staff recommends moving forward with the construction of the park.     

 

FISCAL & STAFF IMPACT:    The amount appropriated for land acquisition, design, engineering, and construction are as follows:

Land acquisition $ 552,701.00

Design $ 150,000.00

Construction $1,474,454.00

Total $2,177,155.00   

         

 

RECOMMENDATION:  Staff recommends that the Board of Aldermen adopt attached resolution.